Alfred St

See UPDATE below this NOTIFICATION 

 

Stateline Asphalt Pty Ltd has been contracted to construct the proposed raised pedestrian crossings at the roundabout in Alfred St South and Fitzroy St. Details are provided below.

Street Alfred St and Fitzroy St, Milsons Point

Location both sides of the roundabout (refer overleaf)

Start Date Monday 24 May 2021

Std Working Hours Mon-Fri 7am to 5pm

Duration 4 weeks (Weather Permitting)

 

The work will consist of laying new drainage pipes, median islands, paved raised pedestrian crossing, new line marking and signage.

Parking in the vicinity of the work site will be unavailable during the works. Residents are requested to move all vehicles from the area indicated by barricades and special work zone signs by 6am on the above commencement date and no vehicles be parked in this area during the works without the contractor’s permission. Failure to comply with this request will only delay the completion of the works and prolong the loss of parking spaces.

 

Traffic control will be utilised to safely manage traffic. Pedestrians AND vehicles will be detoured around the work site.

All effort will be made to minimise disruption and complete the works as quickly and safely as possible.

Council appreciates your cooperation and patience.

 

If you require further information, please do not hesitate to contact Stateline Asphalt on 0416 504 010. Alternatively, you can contact Council’s Engineering Project Manager,

Ashraf Doureihi, on 0421 020 129 or ashraf.doureihi@northsydney.nsw.gov.au

alfredSt.jpg

  

Updated Information

Alfred St and Fitzroy St

Raised Pedestrian Crossings                               

Further to Council’s previous notification letter, Council has been subsequently advised by the Traffic Management Centre (TMC) work on Fitzroy St is to be restricted between 10am to 2:30pm. These restrictions will adversely impact the local community by extending the construction duration from 2 weeks to 4 weeks. Due to these restrictions imposed on Council, some works will now be undertaken at night to help minimise the overall environmental impact. Most of the works will still be undertaken during the day.

 

The tables below outline the construction timetable for both crossings and the impact of the TCM restrictions.

 

Fitzroy St Crossing

Activity

Original Program

Impact on Original Program due to TMC Restrictions

Proposed new Program

 

Day

Night

Day

Night

Day

Night

Drainage

4 days

 

5.5 days

 

5.5 days

 

Construct concrete platform

4 days

 

5.5 days

 

 

2 nights

Lay interlocking paving

2 days

 

4.5 days

 

 

1 night

Construct kerb nibs

2 days

 

4.5 days

 

4.5 days

 

Construct Islands

1 day

 

2 days

 

2 day

 

Lay asphalt correction course

1 day

 

2 days

 

2 day

 

Linemarking

 

1 night

 

1 night

 

1 night

TOTAL DURATION

15 days (2 weeks, including Sat)

24 days (4 weeks, including Sat)

17 days (2.5 weeks, including Sat)

 

Alfred St Crossing

Activity

Original Program (unchanged)

 

Day

Night

Drainage

4 days

 

Construct concrete platform

4 days

 

Lay interlocking paving

2 days

 

Construct kerb nibs

2 days

 

Construct Islands

1 day

 

Lay asphalt correction course

1 day

 

Linemarking

 

1 night

TOTAL DURATION

12 days (2 weeks, including Sat)

 

Residents will be advised ahead of time of the nights works via the existing 3 digital sign boards displayed at the roundabout.

Residents are again reminded that parking in the vicinity of the work site will be unavailable during the works. Residents are requested to move all vehicles from the area indicated by barricades and special work zone signs by 6am on the below construction commencement date and no vehicles be parked in this area during the works without the contractor’s permission. Failure to comply with this request will only delay the completion of the works and prolong the loss of parking spaces.

 

Fitzroy St Crossing

  • Start Date

    • preparatory works      Monday 24 May 2021

    • construction works     Monday 31 May 2021

  • Working Hours                    Mon-Fri 7am to 5pm

  • Intermittent night works       7pm-5am

  • Duration                              2.5 weeks (Weather Permitting)

 

Alfred St Crossing

  • Start Date                            Thursday 17 June 2021

  • Working Hours                    Mon-Fri 7am to 5pm

  • Duration                              2 weeks (Weather Permitting)


Traffic control will be utilised to safely manage traffic. Pedestrians AND vehicles will be detoured around the work site.

All effort will be made to minimise disruption and complete the works as quickly and safely as possible.  Council appreciates your cooperation and patience.

If you require further information, please do not hesitate to contact Stateline Asphalt on 0416 504 010. Alternatively, you can contact Council’s Engineering Project Manager, Ashraf Doureihi, on ashraf.doureihi@northsydney.nsw.gov.au

 

Yours faithfully, 