Ben Boyd Rd cnr Hardie St

Notice of Pedestrian Crossing & Stormwater Drainage Works

Ben Boyd Road & Hardie Street, Neutral Bay

 

North Sydney Council has engaged Civotek to upgrade the Pedestrian Crossing & construct a new Stormwater Drainage System on Ben Boyd Road between Lindsay St & Hardie Street, Neutral Bay.

It is anticipated that the works will commence on Monday 28 of June 2021 and will be completed within 5 weeks, weather permitting. Working hours will be between 7.00am and 5.00pm (Mon-Fri) and 8.00am -1.00pm (Sat).

All steps will be taken to maintain pedestrian and vehicular access whilst work is in progress. There may be short periods of time where access will be unavailable, e.g., during excavation or when concrete is being placed. There will be traffic diversions in place at times, however, local traffic and customers will be provided access by dedicated traffic control personnel.

If you have any further enquiries, please contact Civotek Project Manager Rawi Sader on 0450 494 791 or Council representative Robert Esdaile on 9936 8100 or robert.esdaile@northsydney.nsw.gov.au

We hope that we do not cause you too much inconvenience and would like to thank you in anticipation for your cooperation throughout the work.

Yours sincerely, Civotek Team