Carter St

Carter Street Pedestrian Crossing Upgrade Works                       

EzyPave Pty Ltd has been contracted to carry out works for Council. Details are provided below.

  • Street                          Carter Street, Cammeray (refer to locality map on back page)
  • Location                     Between Bellevue St and Colin St
  • Start Date                  Thursday 10 - June 2021
  • Working Hours         Monday-Friday 7am to 5pm, Saturday 8am to 2pm.
  • Duration                    up to 2 weeks (Weather Permitting)

 

The nature of the upgrade works will comprise new pedestrian crossing, kerb and gutter, kerb ramps and Linemarking.

Parking on Carter St and Colin St will be limited during the works. Residents are requested to move all vehicles from the area indicated by barricades and special work zone signs by 6am on the above commencement date and no vehicles be parked in this area during the works without the contractor’s permission. Failure to comply with this request will only delay the completion of the works and prolong the loss of parking spaces.

Traffic control will be utilised to safely manage traffic. Pedestrians and traffic will be detoured around the work site.

All effort will be made to minimise disruption and complete the works as quickly and safely as possible.  Council appreciates your cooperation and patience.

If you require further information, please do not hesitate to contact EzyPave on (0450 800 603). Alternatively, you can contact Council’s Engineering Project Manager, Ashraf Doureihi, on 0421 020 129 or ashraf.doureihi@northsydney.nsw.gov.au