Kirribilli Seawall works

Shamrock Developments International Pty Ltd has been contracted to carry out seawall works for Council. Details are provided below.

 Street Jeffreys St, Kirribilli

 Location Captain Henry Waterhouse Reserve (refer map below)

 Start Date Monday 15 February 2021

 Working Hours 7am to 5pm, Monday to Friday 8am to 2pm, Saturday

 Duration 3 weeks (Weather Permitting)

 

The work will involve drilling, grouting and sandstone works on the sea wall.

Pedestrians will be detoured around the work site and access to residences will always be maintained. All effort will be made to minimise disruption and complete the works as quickly and safely as possible. Council appreciates your cooperation and patience.

 

If you require further information, please do not hesitate to contact the site manager, Michael Reidy, on 0413671225 or at michaelreidy@shamrockdevelopments.com.au.

Alternatively, you can contact Council’s Engineering Project Manager, Ashraf Doureihi, on 9936 8232 or at ashraf.Doureihi@northsydney.nsw.gov.au

Yours faithfully, NORTH SYDNEY COUNCIL 