Kurraba Rd

Shamrock Developments International Pty Ltd has been contracted to construct the proposed raised pedestrian crossing in Kurraba Rd near Hayes St. Details are provided below.

  •  Street Kurraba Rd, Neutral Bay
  •  Location near Hayes St (refer overleaf)
  •  Start Date Monday 10 May 2021
  •  Std Working Hours Mon-Fri 7am to 5pm
  •  Intermittent Night Works 7pm – 1am
  •  Duration 3 weeks (Weather Permitting)

The work will consist of laying new drainage pipes, median islands, paved raised pedestrian crossing, new line marking and signage.

Parking in the vicinity of the work site will be unavailable during the works. Residents are requested to move all vehicles from the area indicated by barricades and special work zone signs by 6am on the above commencement date and no vehicles be parked in this area during the works without the contractor’s permission. Failure to comply with this request will only delay the completion of the works and prolong the loss of parking spaces.

Traffic control will be utilised to safely manage traffic. Pedestrians AND vehicles will be detoured around the work site.

Due to working restrictions imposed by the Traffic Management Centre (TMC), some aspects of the works may unfortunately be carried out at night.

All effort will be made to minimise disruption and complete the works as quickly and safely as possible. Council appreciates your cooperation and patience.

Temporary parking permits will be available from the contractor for residents impacted by the works and who cannot park in their driveway.

If you require further information, please do not hesitate to contact Shamrock Developments International on 0413 671 225. Alternatively, you can contact Council’s Engineering Project Manager, Ashraf Doureihi, on 0421 020 129 or ashraf.doureihi@northsydney.nsw.gov.au

 

kurraba.JPG

Project Location

Back to Listing