Miller St Pavement Resurfacing Works Stage 2 (Night Works)                                

Stateline Asphalt Pty Ltd has been contracted to carry out works for Council. Details are provided below.

  • Street                    Miller St, North Sydney

  • Location                between Berry St and McLaren St (refer overleaf)

  • Start Date              Friday 2 August 2019

  • Working Hours      9pm to 5am, Monday to Friday

  • Duration                up to 3 weeks (Weather Permitting)

The work will involve stripping the asphalt layer to expose the underlying concrete base, undertake slab repairs as necessary and then reseal the road full width.

 

Due to restrictions imposed on Council by the Traffic Management Centre, these works can only be undertaken at night.

 

Parking in the vicinity of the work site will be unavailable during the works. Residents/Business Owners are requested to move all vehicles from the area indicated by barricades and special work zone signs by 7pm on the above commencement date and no vehicles be parked in this area during the works without the contractor’s permission. Failure to comply with this request will only delay the completion of the works and prolong the loss of parking spaces.

Traffic control will be utilised to safely manage traffic. Pedestrians AND vehicles will be detoured around the work site.

All effort will be made to minimise disruption and complete the works as quickly and safely as possible.  Council appreciates your cooperation and patience.

 

If you require further information, please do not hesitate to contact Stateline Asphalt on 0416 504 010.

Or, contact Council’s Engineering Project Manager, Ashraf Doureihi, on 0421 020 129 or ashraf.doureihi@northsydney.nsw.gov.au

 