Civeco has been engaged by North Sydney Council to undertake the stormwater rehabilitation and associated civil works at Undercliff St, Neutral Bay.

The construction works are between Ben Boyd Rd and Reserve St. The works involve the following:

  • Construction of new stormwater drainage pipes and pits adjacent to the kerb and gutter.
  • Reconstruction of existing footpath and driveways.
  • Reconstruction of kerb and gutter.

The works are scheduled to commence on Monday 29 April with an anticipated duration of 4 weeks, weather permitting.

Due to the constraints of the site and to ensure the safety during the works Undercliff St will be closed to general traffic and the parking available will be reduced for the duration of the works. However, residents will have access to properties and pedestrian access will be maintained for the duration of the works

The nature of the works means that at times property owners will have restricted vehicular access via their driveways for short amount of time during adjacent works. To ensure that the inconvenience is minimised we will liaise in person with all affected property owners prior to this work being completed. We encourage residents to enquire with our on-site staff should they have any queries or concerns regarding programming once the project has commenced.

We strive to complete the works in a swift and professional manner, minimising disturbances where possible. Should you have any queries or concerns, please contact our Project Manager for the works, Nakhly on 0424 343 449 or alternatively, Council’s Engineering Project Manager, Jim Moore on 9936 8233.