Approved out of hours works

Go back to web version

Print version

Current out of hours works

View current out of hours works approved by Council

The following works are scheduled to take place outside of approved construction hours.

Council only approves work outside approved construction hours in specific circumstances. Examples include overnight shop fit-outs or where demolition, excavation or erection of structures may be a risk to public safety during daylight hours.

Approved hours of work

The approved hours of work for a specific development site are contained in the Development Consent.

You can view the Development Consent for each site via our application tracker.

Application tracker

Please note, we are not the only authority who can approve out of hours works. There may be additional approved works we are not aware of (for emergencies, water works etc).

Navigating this page

View current works by clicking next below or clicking the links in the box at the top of the page.

Works by other authorities

Third parties, such as utility companies and state departments, do not have to notify Council of emergency works.

For more details on out of hours works being carried out in your area, check with the following organisations:

Denison Street, North Sydney

Works: Sydney Water inspection of Stormwater Infrastructure

Work dates: Works will take place on Monday 30 March, 8pm to 5am, weather permitting 

Contact: Will Townsend, Senior Project Engineer, 0437 010 517

Denison Street, North Sydney

Works: Repainting façade using EWP

Work dates: Works will take place over a period of 10 nights, between the hours of 7pm to 3am, weather permitting. Work dates include:

  • Monday 30 March to Wednesday 1 April
  • Wednesday 8 April to Friday 10 April 
  • Monday 13 April to Wednesday 15 April
  • Friday 17 April 

Contact: Will Townsend, 0413046545

Albany St, Willoughby Rd, Crows Nest

Council has approved a film permit in accordance with the NSW Local Government Film Protocol, following a thorough assessment to ensure compliance with all relevant guidelines and community expectations.
As part of this process, Council’s Traffic Team has carefully reviewed the proposed activity, including traffic management plans, vehicle movements, crew operations, parking arrangements, and any anticipated impacts on local roads or pedestrian access.


Location(s):

  1.  Albany Street, Crows Nest
  2.  Willoughby Rd, Crows Nest


Filming date/time:

Date: 27 March, 2026

Time: 1:30pm to 8:30pm


Parking/barricading to commence from 7am and vacated by 8:30pm:

  •   15 parking spaces to be taken up on Albany Street
  •   4 parking spaces on Willoughby Rd


Traffic requirements

All potential issues—such as noise, brief interruptions to traffic flow, or changes to usual access—have been fully considered, and appropriate mitigation measures have been put in place to minimise disruption to residents, businesses, and visitors.
With these controls in place and the production is required to adhere to strict conditions that the filming activity will proceed safely, efficiently, and with minimal impact on the surrounding community.
If you have any further enquiries or encounter any issues on the relevant date(s), please use the contact details below:


Contact:
Damon Wilder

0431 060 985

227 Ben Boyd Rd, Neutral Bay

Works:
Asphalt Road Restoration Works

Work dates:
Commencing Monday 30 March, 2026, for four nights from 7pm to 5am, weather permitting. 

177 Walker St, North Sydney

Works:
Oversized vehicle movement – removal of large plant from site

Work dates:
Works will take place on Wednesday 26 March 2026, between 2am and 5am

Contact: 
Jack Chaouka - jack.c@aland.com.au  - 0432241884