View current out of hours works approved by Council

The following works are scheduled to take place outside of standard construction hours. The standard construction hours are listed below.

Council only approves work outside standard construction hours in specific circumstances. Examples include overnight shop fit-outs or where demolition, excavation or erection of structures may be a risk to public safety during daylight hours.

Please note, we are not the only authority who can approve out of hours works. There may be additional approved works we are not aware of (for emergencies, water works etc).

Standard construction hours

Monday to Friday

  • 7am - 7pm (for B3 Commercial Core and B4 Mixed Use)
  • 7am - 5pm (for all other zones)

Saturday

  • 8am - 1pm

Standard demolition and excavation hours

  • Monday to Friday only, between 8am and 5pm

Navagiting this page

View current works by clicking next below or clicking the links in the box at the top of the page.

Alexander and Falcon Street, Crows Nest

Works: sewerage deviation works

Contact: Ishmam Muhammad  - Kwikflo Group, 0480 432 178, hh@kwikflogroup.com.au

Work dates: Monday 23 June to Wednesday 2 July, 9pm to 5am, Monday to Wednesay, weather permitting.

Falcon Street, Crows Nest

Works: Crane activity, lifting aircon units to building

Contact: Dennis Dandolo, Safeway, 0403 323 290

Work dates: Works will take place on Monday 30 June, 2am to 6am, weather permitting.

Miller Street, North Sydney

Works: Removal of substation kiosk

Work dates: works will take place on Monday 23 June to Wednesday 25 June, 9pm to 5am Monday to Friday, weather permitting.

Works: Tower crane dismantle

Work dates: The requested duration for standing plant activity is Saturday 28 June, 7am-7pm, weather permitting.

Contact: Cameron Garth, Lendlease, 0438735450

Tunks Park Boat Ramp

Works: maintenance works

Contact: Shamrock Developments International, 0413 671 225

Work dates: works will commence on Tuesday 24 June and are expected to be completed within 4 days, 7am to 5pm and 11pm to 6am Monday to Friday, weather permitting.

Letter to residents

Alexander Street, Crows Nest

Works: demolition of the corner building requiring electrical shut down

Work dates: works will take place on Sunday 29th June 8pm to 5am (Electrical shutdown), Monday 30 June 7am to 5pm, Tuesday 1 July 7am to 5pm and Wednesday 2 July 7am to 5pm, weather permitting

Contact: Matthew Young, Deicorp, 0467370380

 

 

Rosalind Street and Miller Street, Cammeray

Works: construction of two new pedestrian crossings

Works dates: Works will commence Monday 7 July and be completed within 2 weeks, between 7am and 5pm. Line marking to be completed between 7pm to 11pm over one shift.

Contact: Rawi Sader, Civotek, 0450 494 791

Letter to residents

Works by other authorities

Third parties, such as utility companies and state departments, do not have to notify Council of emergency works.

For more details on out of hours works being carried out in your area, check with the following organisations:

Go back to web version