Council road and infrastructure works

Go back to web version

Print version

When Council or Council's contractor undertakes infrastructure or road works, we must follow standard working hours.

Standard construction hours

Monday to Friday

  • 7am - 7pm (for B3 Commercial Core and B4 Mixed Use)
  • 7am - 5pm (for all other zones)

Saturday

  • 8am - 1pm

Standard demolition and excavation hours

  • Monday to Friday only, between 8am and 5pm

Start and end times are estimates only (weather and other factors permitting). All efforts will be made to minimise disruption and complete the works as quickly and safely as possible. Council appreciates your cooperation and patience.

Council may approve construction works outside of standard hours for public safety reasons.

View current Council or contractor works

View current works by clicking next below or clicking the links in the box at the top of the page.

Willoughby Road, Crows Nest

Works: Ausgrid is in the process of undergrounding the overhead power cables on Willoughby Road from Burlington Street to Albany Street.

Works dates:

  • 5 and 6 May 2025 from 7.30am – on either side of the Willoughby Road footpath entrance to the number 90 Public Arcade
  • 6 May 2025 from 7.30am – on the footpath outside number 56 shop 
  • 6 May 2025 from 7.30am – on Albany St (south west side) near the corner of Willoughby Road

Contact: Garde Services Pty Ltd 02 9737 9062, email community@garde.com.au

Note: There will be NO power interruptions.

More information about the Willoughby Road upgrade.

Blues Point Reserve

Works: upgrading the pathway lighting

Contact: Ali Herz, TOBCO, 0450506445

Work dates: Tuesday 24 March to Sunday 15 June, 7am to 5pm Monday to Friday, weather permitting.

Letter to residents

 

Hipwood Street and Bradly Avenue, Kirribilli

Works: a new concrete driveway in Milson Park

Contact: Rawi Sader, Civotek Project Manager, 0450 494 791

Work dates: Works will commence Monday 26 May and will be completed within one week, 7am to 5pm Monday to Friday, weather permitting. 

Letter to residents

MacCallum Pool, Cremorne

Works:rock stabilisation and retaining wall works

Contact: Anthony Anzellotti, Anzellotti Constructions, 0418 223 302

Work dates: Works will commence Monday 2 June and will be completed within three weeks, 7am to 5pm Monday to Friday, weather permitting. 

Letter to residents

 

Kareela Road, Cremorne Point

Works: maintenance works on the retaining wall in Kareela Road

Contact: Civil Landscaping, 0430 592 240

Work dates: Works will commence Wednesday 11 June and will be completed within 5 days, 7am to 5pm Monday to Friday and Sat 8am to 1pm, weather permitting. 

Letter to residents 

Abbott Street and Palmer Street, Cammeray

Works: removal of drainage converters, new drainage pipes, new drainage pits, concrete kerb and gutter, minor footpath replacement and minor landscaping.

Contact: Ali Makouk, EzyPave, 0450 090 759

Work dates: Works will commence Monday 16 June and will be completed within four weeks, 7am to 5pm Monday to Friday and 8am to 1pm Saturday, weather permitting.

Letter to residents

 

 

 

Go back to web version