Council road and infrastructure works

Go back to web version

Print version

When Council or Council's contractor undertakes infrastructure or road works, we must follow standard working hours.

Standard construction hours

  • Monday to Friday - 7am to 5pm
  • Saturday - 8am to 1pm
  • Sunday and Public Holidays - no work is permitted

Standard demolition and excavation hours

  • Monday to Friday only, between 8am and 5pm

Start and end times are estimates only (weather and other factors permitting). All efforts will be made to minimise disruption and complete the works as quickly and safely as possible. Council appreciates your cooperation and patience.

Council has a management plan for Out of Hours works which provides additional guidance.

View current Council or contractor works

View current works by clicking next below or clicking the links in the box at the top of the page.

Willoughby Road, Crows Nest

Works: underground the overhead power cables

Contact: Garde Services, 02 9737 9062

Work dates: Works will commence in October 2023 and finish in May 2024, weather permitting.

Letter to residents

 

Works: stormwater drainage construction

Contact: Edmond Nouneh, Ally Civil, 0416 538 083

Work dates: Works will commence on Monday 11 March and will finish in June 2024, weather permitting.

Letter to residents

 

Works: footpath paving works

Contact: Edmond Nouneh, Ally Civil, 0416 538 083

Work dates: Works will commence on Monday 6 May and will finish in June 2024, weather permitting.

Letter to resident and business owners

 

More information about the Willoughby Road upgrade.

Bent Street, Neutral Bay

Works: retaining wall works

Contact: Shamrock Developments International, 0413 671 225

Work dates: Works will commence 11 March and finish 13 May, weather permitting.

Letter to residents

Crows Nest Road, Waverton

Works: Upgrade works at the intersection of Crows Nest Road and Carr Street, Waverton, including kerb and gutter extensions, reconstruction of kerb ramps and footpaths, modification of drainage pit lids, and construction of a new roundabout and traffic islands.

Contact: Mohammad Karim, EzyPave, 0410 828 975

Work dates: Works will commence 2 April and be completed within six weeks, weather permitting. A site compound will be established from 25 March, occupying up to three parking spots.

Letter to residents

North Sydney CBD

Works: footpath granite restoration works

Contact: Shamrock Developments International, 0413 671 225

Work dates: Works will commence 19 March and be completed within three weeks, weather permitting.

Letter to residents and business owners

Honda Road, Cremorne Point

Works: stormwater improvement works

Contact: Kevin Azzopardi, Azbuild, 0416 121 099

Work dates: Works will commence Monday 8 April and be completed within eight weeks, weather permitting.

Letter to residents

Reynolds Street, Cremorne

Works: footpath, kerb and gutter reconstruction and drainage works

Contact: Rawi Sader, Civotek, 0450 494 791

Work dates: Works will commence Monday 8 April and be completed within three weeks, weather permitting.

Letter to residents

Balls Head Drive, Waverton

Works: footpath, kerb and gutter, and disabled parking spot construction

Contact: Rawi Sader, Civotek, 0450 494 791

Work dates: Works will commence Tuesday 2 April and be completed within one week, weather permitting.

Letter to residents

Burton Street Plaza, Kirribilli

Works: construction of the permanent Burton Street Plaza including new stormwater drainage, footpath paving, street and decorative lighting, street furniture, sandstone benches with timber top seating around the outdoor dining areas, improved landscape areas and four new trees

Contact: Moe Karim, EzyPave, 0410 828 975

Work dates: Works will commence Monday 15 April and be completed within 10 weeks, weather permitting.

Letter to residents

Park Avenue and Military Road, Neutral Bay

Works: construction of new continuous footpath

Contact: Rawi Sader, Civotek, 0450 494 791

Work dates: Works will be undertaken between 8pm and 5am, beginning Monday 15 April. They will be completed within two weeks, weather permitting.

Letter to residents

Little Spring Street, North Sydney

Works: restoration of concrete pavement and pavement upgrade

Contact: EzyPave, 0410 828 975

Dates: Monday to Friday starting 22 April 2024, 9pm to 5am, for two weeks (weather permitting)

Letter to residents

Cremorne Plaza, Cremorne

Works: geotechnical investigation

Contact: Diana Mejia, North Sydney Council, 02 9936 8434

Dates: Wednesday 17 April 2024, 8.30am to 5pm

Letter to residents

Florence Street and Spofforth Street, Cremorne

Works: upgrading the footpath, kerb and gutter, and pedestrian refuge

Contact: Rawi Sader, Civotek, 0450 494 791

Dates: Works will commence on Monday 22 April 2024 and be completed within two weeks, weather permitting.

Letter to residents

Go back to web version