Walker Street
Location:
Walker Street
Works:
Section 73 sewer minor works, including trench excavation and restoration.
Equipment to be used includes a delivery truck, excavator, and concrete truck with pump.
Work dates:
Works will take place at night between 7:00pm and 5:00am, weather permitting, as follows:
- Night 1 – Monday 29 June 2026: Road opening and sewer trenching (7 parking spaces).
- Night 2 – Tuesday 30 June 2026: Road opening and sewer trenching (7 parking spaces).
- Night 3 – Wednesday 1 July 2026: Contingency road work/reinstatement (7 parking spaces) and footpath opening and sewer trenching.
- Thursday 2 July 2026: Break night - no works.
- Night 4 – Friday 3 July 2026: Footpath reinstatement and completion.