Prepare a Construction Traffic Management Plan

A construction traffic management plan (CTMP) assesses impacts on the local road network created by development.

As a condition of development consent, some developments are required to lodge a construction traffic management plan for approval.

Your report must reflect our standard requirements and provide a description of the proposed construction works, the traffic impacts on the local area and how they'll be addressed.

What you need to do
 

1. Prepare your construction traffic management plan

Use the following guide to ensure it’s adequate for review.

How to Complete a Construction Traffic Management Plan (CTMP) Report

2. Complete the standard requirements

Council's standard requirements must be attached to the CTMP report as an appendix.

The parts in blue will need to be completed on a site-specific basis.

Standard Requirements for a Construction Traffic Management Plan (CTMP)

3. Lodge the CTMP report and ‘Satisfy DA Consent Condition’ application form

When your report is completed and you have filled out the Satisfy DA Consent Condition application form, lodge both documents via email to customerservice@northsydney.nsw.gov.au

An administration fee of $470.00 applies for all applications to Satisfy DA Consent Condition, our Customer Service team will email you a payment link once your application is lodged.

Satisfy DA Consent Condition Application Form

Contact Council

Our Customer Service Centre operates from 9am to 5pm. Our Council Rangers are on duty and contactable seven days a week from 5.30am to midnight.

Address: Customer Service Centre, 200 Miller Street, North Sydney, NSW 2060

Telephone: (02) 9936 8100