Fees

All fees must be paid prior to works commencing and within 24 hours of Customer Service emailing the B-point link for payment.

Service Fee

Initial non-refundable application fee

$200   

To be invoiced by Council at a later date: 

Service Fee
Parking spaces (regardless of kerb side restriction)

$350 (per metered space, per day)

$240 (per non-metered space, per day)

$240 (per lane being closed/occupied)

Skip bin (maximum of 2 weeks) see parking restrictions
Footpath Occupancy (retains consistent 1.2m footpath width) $5 per m2/per day

Footpath occupancy (if footpath is closed and pedestrians are forced to cross the road during works)

$10 per m2, per day
Digging/excavation/opening Restoration fees are site-dependent and include parking and footpath occupancy fees
Temporary full road closure $1990 plus parking per day
Out of hours construction $680 for 3 nights per week
Change of date (5 business days notice, 3 if due to weather) $120